Home
|
Table of Contents
|
Overview Map
Lutron Puerto Rico IPS Safe Passage Project Plan
Dave Lentz 609-790-7834
dave.lentz@avnet.com
Home
1. Safe Passage Implementation Pr...
2. Implementation Team
3. Financial Modeling - Credit S...
4. Agreements/Ts and Cs
5. Operational Set up
6. Establish Material Trigger Rel...
7. Material Preparation
8. Shipping and Handling Special...
9. Invoicing/Payment
Review the order-to-receipt pr...
10. Solution Specific Actions
9.
Invoicing/Payment
Task Information
Task Priority
None
Start - Due Date
12/3/2009
-
12/18/2009
% Complete / Duration
0%
of
12 Day(s)
Resources
Review the order-to-receipt process with accounting
Task Information
Task Priority
None
Start - Due Date
12/3/2009
-
12/18/2009
% Complete / Duration
0%
of
12 Day(s)
Resources
Develop process steps needed to insure prompt payment for the Avnet product received?
Task Information
Task Priority
None
Start - Due Date
12/3/2009
-
12/16/2009
% Complete / Duration
0%
of
10 Day(s)
Resources
SCSM
See related topics and documents
Elevate any requests for summary billing or evaluated receipts payment or special payment models
Elevate any requests for summary billing or evaluated receipts payment or special payment models
Task Information
Task Priority
None
Start - Due Date
12/17/2009
-
12/18/2009
% Complete / Duration
0%
of
2 Day(s)
Resources
SCSM;SC Operations;Customer Accts. Payable
Top
Your Home for design and supply chain needs
Last updated:
10/5/2009