6. Establish Material Trigger Release and/Or Consumption process Priority 1 Task start
Task Information
Task Priority 1
Start - Due Date 11/23/2009 - 12/29/2009
% Complete / Duration 0% of 27 Day(s)
Resources
Determine how Customer will structure their System to receive material Task start
Task Information
Task Priority None
Start - Due Date 11/25/2009 - 12/4/2009
% Complete / Duration 0% of 8 Day(s)
Resources SCSM;SC Operations
Develop Process for Triggering of Release or Material Consumption Task start
Task Information
Task Priority None
Start - Due Date 11/23/2009 - 12/29/2009
% Complete / Duration 0% of 27 Day(s)
Resources
Manual Release via Email / Purschase order/ Consumption Billing/ Other Task start
Task Information
Task Priority None
Start - Due Date 11/23/2009 - 12/17/2009
% Complete / Duration 0% of 19 Day(s)
Resources
Establish process for managing order fulfillment or Billing Task start
Task Information
Task Priority None
Start - Due Date 11/23/2009 - 12/17/2009
% Complete / Duration 0% of 19 Day(s)
Resources SCSM
EDI Task start
Task Information
Task Priority None
Start - Due Date 11/24/2009 - 12/29/2009
% Complete / Duration 0% of 26 Day(s)
Resources
If customer is already transmitting EDI 850, arrange for testing of the transmission format with EDI support Task start
Task Information
Task Priority None
Start - Due Date 11/24/2009 - 12/8/2009
% Complete / Duration 0% of 11 Day(s)
Resources SCSM
If not, supply EDI850 maps to customer establish date for completion of mapping process Task start
Task Information
Task Priority None
Start - Due Date 12/9/2009 - 12/29/2009
% Complete / Duration 0% of 3 Week(s)
Resources
Arrange for testing of the transmission format with EDI Support Task start
Task Information
Task Priority None
Start - Due Date 12/9/2009 - 12/29/2009
% Complete / Duration 0% of 15 Day(s)
Resources SCSM